What is the Project?
The City of Medicine Hat is building a new electrical substation to support growing electrical demand in the southwest area of the city and surrounding region.
The project was approved by the Alberta Utilities Commission (AUC) on April 25, 2025 (Proceeding #29734), allowing construction and operation at the previously identified Preferred Site. More information about the project is available in the AUC Decision document.
Construction Update
Construction will begin in June 2026.
As preparation work gets underway, you may notice equipment and activity at the site. Click to view a map of the approved project components and construction access. The substation is anticipated to be in service in early 2027.
How can you get involved?
Thank you to everyone who has participated in this project to date. Your input has helped shape the process.
The project team will continue to share updates and remain available to answer questions as construction progresses. We encourage you to sign up for email notices to stay informed about upcoming construction activities.
If you have any questions or concerns, or wish to review previous project materials, please contact our project team.
What is the Project?
The City of Medicine Hat is building a new electrical substation to support growing electrical demand in the southwest area of the city and surrounding region.
The project was approved by the Alberta Utilities Commission (AUC) on April 25, 2025 (Proceeding #29734), allowing construction and operation at the previously identified Preferred Site. More information about the project is available in the AUC Decision document.
Construction Update
Construction will begin in June 2026.
As preparation work gets underway, you may notice equipment and activity at the site. Click to view a map of the approved project components and construction access. The substation is anticipated to be in service in early 2027.
How can you get involved?
Thank you to everyone who has participated in this project to date. Your input has helped shape the process.
The project team will continue to share updates and remain available to answer questions as construction progresses. We encourage you to sign up for email notices to stay informed about upcoming construction activities.
If you have any questions or concerns, or wish to review previous project materials, please contact our project team.
Share Approved site renderings on FacebookShare Approved site renderings on TwitterShare Approved site renderings on LinkedinEmail Approved site renderings link
What might the Project look like?
The City of Medicine Hat has renderings of the approved Medicine Hat Southwest Substation. These renderings are designed to assist with understanding how the proposed project may look on the landscape from three separate viewpoints.
Each file contains three images:
Existing landscape
Proposed infrastructure
Proposed infrastructure (yellow)
These files are large and will take time to download. Due to differing internet speeds or the method of downloading, we have provided two types of files – high resolution and lower resolution.
The City of Medicine Hat has renderings of the approved Medicine Hat Southwest Substation. These renderings are designed to assist with understanding how the proposed project may look on the landscape from three separate viewpoints.
Each file contains three images:
Existing landscape
Proposed infrastructure
Proposed infrastructure (yellow)
These files are large and will take time to download. Due to differing internet speeds or the method of downloading, we have provided two types of files – high resolution and lower resolution.